Otjimbingwe Proclamation
- Town land boundaries surveyed and declared.
- Establishment of township in process
- Plots surveyed
- Diagrams handed in for approval
Electricity
- Electricity designs for all plots 100% completed.
- 40 % of surveyed plots are serviced with electricity under rural electrification and Regional Council funding.
Sewerage
- Sewerage designs are 100% completed.
- 40% of surveyed plots are serviced with sewerage.
Water
- Water designs are 100% completed.
- All surveyed plots are serviced with water (100% completed).
- All water consumers installed with water-prepayment meters.
Streets
- Streets designs are 100% completed, however no construction has started as yet.
Refuse Removal
- All occupied plots are serviced with refuse removal.
|